The challenge
A redundant below-ground pit at the site had reached the end of its working life and was to be permanently taken out of use by filling it with concrete. Before it could be filled it had to be completely emptied and cleaned out.
The pit was a deep, enclosed concrete structure holding standing liquid, oily residue and silt, with pipework and access covers still in place. Working at the bottom of a structure like this is a confined-space operation, so the clean-out had to be planned and controlled accordingly, and everything taken out of it had to be classified and disposed of correctly rather than washed away.
What we arranged
AES managed the job from survey to completion, appointing and overseeing vetted, licensed operatives and specialist providers rather than collecting or moving anything ourselves.
- Survey. We established what the pit contained and how it was accessed, and planned the confined-space controls before any work began.
- Emptying. The standing liquid, oily residue and silt were pumped and drawn out through suction hoses and vacuumation equipment brought in for the job.
- Cleaning. The pit walls and floor were cleaned down and left sound and ready for the infill.
- Disposal. The recovered liquid and sludge were classified and their compliant disposal arranged through registered carriers to a permitted facility.
- Preparation for infill. With the pit clean and empty, it was prepared so the concrete infill could be placed to take the structure permanently out of service.
The result
The pit was emptied and cleaned out and left ready to be filled, closing off a redundant below-ground void that was no longer needed.
The recovered liquids and sludge were removed from site and disposed of through a permitted route, and the duty-of-care file went back with the job: a transfer or consignment note for every movement, the classification behind each code, and confirmation of the facility that received each stream.
On site
-
The pit during the clean-out, cordoned off and controlled as a confined-space operation. -
The pit opened up and cordoned off in the workshop before the clean-out began. -
Working at the bottom of the pit, planned and controlled as a confined-space operation. -
The process line at the works, giving the setting for the redundant pit being taken out of service.